Delays mean gas from Eni’s Sankofa field is likely to arrive before Ghana’s pipelines and power projects are ready for it Delays mean gas from Eni’s Sankofa field is likely to arrive before Ghana’s pipelines and power projects are ready for it.
By Miriam Malek 18 August 2017 Middle East & Africa / Pipelines, Storage & Power 0 27248
Eni’s Offshore Cape Three Points project in Ghana. Eni)

Delays to two pipeline projects in Ghana could prevent the developers of the offshore Sankofa field from selling their gas to alternative buyers in the event that power projects – the intended customers – are unable to meet their obligations. 

A change in the Ghanaian government earlier this year has delayed work on the pipelines amid a standstill in the review process for some of Sankofa’s offtakers.

One of the connections – the Aboadze-Tema pipeline – could carry Sankofa volumes to different offtakers if the...