Twenty-nine projects are aiming for FID next year, representing 299.3 mtpa of additional liquefaction capacity Twenty-nine projects are aiming for FID next year, representing 299.3 mtpa of additional liquefaction capacity.
By Andrew Walker 6 December 2018 0 33578

North American projects – greenfield and brownfield

1. Lake Charles LNG (16.5 mtpa) The joint venture project by Energy Transfer, Shell and Kogas has a deadline of November 2019 to begin construction on the plant having filed an extension with the Louisiana Department of Environmental Quality in April. The project to repurpose the Lake Charles LNG terminal for export has approval from the US Federal Energy Regulatory Commission (FERC).

2. Magnolia LNG (8.0 mtpa) The Magnolia project being developed by LNG Ltd has received...