The commissioning dates for almost half of PCI projects in the gas and power sectors have been delayed by one or two years The commissioning dates for almost half of PCI projects in the gas and power sectors have been delayed by one or two years.
By Andreas Walstad 18 July 2018 0 31782
Projects of Common Interest by status, gas
Projects of Common Interest by status, electricity

Almost half of EU-backed Projects of Common Interest (PCIs) in the gas and power sectors are facing delays, according to an annual report by the Agency for the Cooperation of Energy Regulators (ACER)

Although a number of projects in the European Commission’s 2017 list of PCIs have advanced since last year, the commissioning dates for almost half have been pushed...