Gazprom completes undersea work on first line of Turkish Stream

Gazprom has completed deepwater operations on the first line of the Turkish Stream pipeline.
By Staff reporter 30 April 2018 0 30647

Gazprom has completed deepwater operations on the first line of the Turkish Stream pipeline, the company said in a note on Monday.

“The [Turkish Stream] pipeline project has been successfully completed and the first stage of the gas pipeline has been built,” Chief Executive Alexei Miller said in a statement. Miller added that a total of 1,161 km of the two offshore streams of Turkish Stream had been built since work started on 7 May 2017.

Gazprom is planning to bring both lines of Turkish Stream into operation...