Project Insights

Interconnector delay weakens Moldova's hand

The Romania-Moldova Interconnector will not be ready until at least August 2020, six months after the expiry date of Moldovagaz’s supply contract with Gazprom The Romania-Moldova Interconnector will not be ready until at least August 2020, six months after the expiry date of Moldovagaz’s supply contract with Gazprom.
By Silvia Favasuli 5 days ago Europe & Russia / Pipelines, Storage & Power 0 34295
Gazprom CEO Alexei Miller (left) and Moldovan President Igor Dodon at their SPIEF meeting. (Gazprom)

A reported six-month delay to the completion of the Romania-Moldova Interconnector will weaken Moldova’s position as it attempts to renegotiate a long-term gas supply deal with Russia’s Gazprom.

Moldova’s current deal was struck in 2016 and expires in December, which is roughly when the interconnector was originally expected to come online. But according to a source close to the project, the pipeline will not be ready until at least mid-2020.

Construction work on the pipeline, which will have a capacity of 1.5 billion cubic metres per year...